web analytics

Mumbai Metro Line 5 (Orange Line): Thane–Bhiwandi–Kalyan Route, Stations & Status

Mumbai Metro

Part of our Mumbai Metro guide — every line, fare, timing and status update in one place.

Mumbai Metro Line 5 (Orange Line) will link Thane, Bhiwandi and Kalyan, starting from Kapurbawdi on Line 4. Phase 1, a 7-station elevated stretch from Kapurbawdi to Dhamankar Naka in Bhiwandi, is in its final stage: a train is now on the line for trial runs, and opening is expected between December 2026 and early 2027, after the safety inspection. A revised plan approved in August 2026 extends the network to Kalyan and Ulhasnagar (Line 5A) by about 2030–31.

Under construction · Phase 1 trial runs under way

Phase 1

Kapurbawdi – Dhamankar Naka · 11.9 km

Phase 1 stations

7 (elevated)

Expected

Dec 2026 – early 2027

Full network

About 34 km (with 5A)

Last checked: November 2026 · Opening dates and fares will be confirmed by MMRDA.

Line 5 route & stations

Phase 1 – final stage Planned · Ⓜ Metro interchange

  • Kapurbawdi Ⓜ Line 4 · Thane
  • Balkum Naka
  • Kasheli depot
  • Kalher
  • Purna
  • Anjur Phata
  • Dhamankar Naka end of Phase 1 · Bhiwandi
  • Bhiwandi planned · underground section
  • Durgadi Kalyan · Line 5A to Ulhasnagar

Full station list

#StationStatusInterchange
1KapurbawdiPhase 1 – final stageLine 4
2Balkum NakaPhase 1 – final stage–
3KasheliPhase 1 – final stage–
4KalherPhase 1 – final stage–
5PurnaPhase 1 – final stage–
6Anjur PhataPhase 1 – final stage–
7Dhamankar NakaPhase 1 – final stage–
8BhiwandiPlanned–
9TemgharPlanned–
10RajnouliPlanned–
11GovegaonPlanned–
12Kongaon (West)Planned–
13Kongaon (East)Planned–
14DurgadiPlannedLine 5A – planned

Phase 2 station names follow the revised alignment approved in August 2026 and may change before construction.

Current status (November 2026)

  • Phase 1: civil work on the 11.9 km Kapurbawdi – Dhamankar Naka stretch is almost complete, and power to the overhead wires was switched on in early October 2026.
  • Trial runs: during Navratri (October 2026), a spare BEML train from Metro Lines 2A and 7 was moved onto Line 5 through Line 4, and trial runs have begun. Line 5 will run on borrowed trains, about every 5–6 minutes, until its own trains arrive in 2027.
  • Kasheli creek: the 550 m creek bridge between Thane and Bhiwandi was completed in January 2023.
  • Revised plan: on 29 August 2026 the Centre approved a revised alignment for Line 5 and the new Line 5A, taking the network to about 34 km with an underground section at Bhiwandi.
  • Kasheli depot: the first train reached the 27-hectare depot in November 2026. The coach unloading platform and a temporary inspection bay are ready; inspection and workshop lines and a test track are still being built.
  • Phases 2 and 3: in July 2026, MMRDA invited bids to build Dhamankar Naka – Durgadi (with about 3 km underground at Bhiwandi) and Kalyan – Ulhasnagar, with 48 months to complete the work.
  • Target: Phase 1 between December 2026 and early 2027, once the Commissioner of Metro Rail Safety (CMRS) clears it; Bhiwandi – Kalyan – Ulhasnagar around 2030–31.

Timings & fare

ItemDetails
TimingsTo be announced
Frequency at launchAbout every 5–6 minutes (expected)
Journey timeAbout 25 minutes from Thane to Bhiwandi, against 45 minutes or more by road at peak hours
FareTo be announced by MMRDA before opening
AuthorityMMRDA
DepotKasheli

Interchange stations

Kapurbawdi

Ⓜ Line 4

Starting point in Thane, near Viviana and Korum malls. Change to Line 4 (Green Line) for Ghodbunder Road, Cadbury Junction and, later, Ghatkopar and Wadala.

Dhamankar Naka

End of Phase 1, serving Bhiwandi’s busy textile and warehousing area.

Durgadi (Kalyan)

Line 5A · Line 12 (planned)

Future junction where Line 5A continues via Kalyan station to Ulhasnagar. Line 12 (Kalyan – Dombivli – Amandoot) will link Kalyan to Navi Mumbai.

Kalyan & Ulhasnagar extension

The original Line 5 plan was a 24.9 km corridor ending at Kalyan APMC. The revised network approved in August 2026 runs about 34 km: Line 5 continues from Bhiwandi through Temghar, Rajnouli, Govegaon and Kongaon to Durgadi, and Line 5A runs from Durgadi via Khadakpada, Bhoirwadi and Kalyan station to Ulhasnagar.

This later phase is targeted for about 2030–31 and is estimated, with Line 5A, at ₹18,130.55 crore.

Route map

See also: Mumbai Metro map – all lines

Timeline

  • October 2016MMRDA approves a 24 km Thane – Bhiwandi – Kalyan metro line.
  • December 2018Foundation stone laid in Kalyan.
  • January 2020Afcons awarded the Kapurbawdi – Bhiwandi civil contract; work starts in February.
  • November 2021Depot shifted to Kasheli.
  • January 2023Kasheli creek bridge completed.
  • June 2023Underground section at Bhiwandi approved.
  • July 2026MMRDA invites bids for Phases 2 and 3 (Dhamankar Naka – Durgadi and Kalyan – Ulhasnagar).
  • 29 August 2026Centre approves revised Line 5 and Line 5A to Ulhasnagar.
  • October 2026Power switched on; a borrowed train is moved onto Line 5 and trial runs begin.
  • November 2026First train reaches Kasheli depot.

About Metro Line 5

Why Line 5 matters

Bhiwandi has no suburban rail link to Thane or Mumbai, and the Thane – Bhiwandi road is one of the most congested in the region. Line 5 gives Bhiwandi its first metro, and later connects it to Kalyan and Ulhasnagar on the Central Railway.

Project & technical details

Phase 1: Kapurbawdi – Dhamankar Naka, 11.9 km, 7 elevated stations, ₹6,741 crore · Full network: about 34 km with Line 5A · Gauge: 1,435 mm standard gauge

Cost: ₹18,130.55 crore (revised Line 5 + 5A) · Civil contractor (Phase 1): Afcons · Depot: Kasheli · Authority: MMRDA

Frequently asked questions

Is Mumbai Metro Line 5 open?

Not yet. Phase 1, from Kapurbawdi in Thane to Dhamankar Naka in Bhiwandi, is in trial runs. MMRDA expects to open it between December 2026 and early 2027, after the Commissioner of Metro Rail Safety (CMRS) inspection. No official opening date has been announced.

What is the route of Metro Line 5?

Line 5 (Orange Line) runs from Kapurbawdi in Thane across Kasheli creek to Bhiwandi and on to Kalyan. A revised alignment approved in August 2026 extends the network to Ulhasnagar as Line 5A.

Which stations open first on Line 5?

Phase 1 has seven elevated stations: Kapurbawdi, Balkum Naka, Kasheli, Kalher, Purna, Anjur Phata and Dhamankar Naka.

Does Line 5 connect with Line 4?

Yes. Kapurbawdi is the interchange with Line 4 (Green Line), which will link Line 5 riders to Ghodbunder Road, central Thane, Ghatkopar and Wadala.

Will Line 5 go to Kalyan and Ulhasnagar?

Yes, in a later phase. The revised plan approved by the Centre in August 2026 continues the line from Bhiwandi (with a short underground section) to Durgadi in Kalyan, and Line 5A runs on via Kalyan station to Ulhasnagar. This extended network is targeted for 2030–31.

What will the fare be on Line 5?

Fares have not been announced yet. MMRDA is expected to announce them before Phase 1 opens.

How much does Line 5 cost?

Phase 1 (11.9 km) costs about ₹6,741 crore. The revised Line 5 and 5A network of about 34 km is estimated at ₹18,130.55 crore in all.

Where is the Line 5 depot?

At Kasheli, between Thane and Bhiwandi.

Why is a part of Line 5 underground?

Near Bhiwandi the elevated route clashed with the Bhiwandi bypass flyover, so the revised alignment takes a short stretch underground.

Have trial runs started on Metro Line 5?

Yes. In October 2026, a spare BEML train from Metro Lines 2A and 7 was moved onto Line 5 through Line 4, and trial runs began on the Thane – Bhiwandi stretch. In November 2026 the first train reached the Kasheli depot.

Other metro lines

Sources: Mumbai Live – Phase 1 this year · Metro Rail News – Centre approves Line 5 & 5A (29 Aug 2026) · Free Press Journal – First train at Kasheli depot (Nov 2026) · Swarajya – Line 5 gets first rake (Oct 2026) · Free Press Journal – Bids for Phases 2 and 3 (Jul 2026) · Wikipedia – Orange Line