Mumbai Metro Line 9 (Red Line): Route, Stations, Timings, Fare & Status

Mumbai Metro

Part of our Mumbai Metro guide โ€” every line, fare, timing and status update in one place.

Mumbai Metro Line 9 (Red Line) is an elevated metro line extending Line 7 north from Dahisar (East) to Mira Road and Bhayandar. The first four stations, from Dahisar (East) to Kashigaon, opened on 8 April 2026, with direct trains from Gundavali in Andheri (East). The remaining four stations to Bhayandar are expected around December 2026.

Partly open ยท Dahisar (East) โ€“ Kashigaon

Timings

5:50 AM โ€“ 11:00 PM

Frequency

Under 6 min at peak

Fare

โ‚น10 โ€“ โ‚น20 (โ‚น50 from Gundavali)

Stations open

4 of 8

Last checked: October 2026 ยท Timings and fares can change โ€” confirm on MMMOCL’s app or website.

Line 9 route & stations

Operational Under construction ยท โ“‚ Metro interchange

  • Dahisar (East) โ“‚ Line 2A ยท โ“‚ Line 7
  • Pandurang Wadi
  • Miragaon โ“‚ Line 10 (proposed)
  • Kashigaon current terminus
  • Sai Baba Nagar
  • Deepak Hospital (Medtiya Nagar)
  • Shaheed Bhagat Singh Garden
  • Subhash Chandra Bose Stadium Bhayandar ยท Line 13 (proposed)

Full station list

#StationStatusInterchange
1Dahisar (East)OperationalLine 2A, Line 7
2Pandurang WadiOperationalโ€“
3MiragaonOperationalLine 10 โ€“ proposed
4KashigaonOperationalโ€“
5Sai Baba NagarUnder constructionโ€“
6Deepak Hospital (Medtiya Nagar)Under constructionโ€“
7Shaheed Bhagat Singh GardenUnder constructionโ€“
8Subhash Chandra Bose StadiumUnder constructionLine 13 โ€“ proposed

Timings & fare

ItemDetails
First trainAround 5:50 AM
Last trainAround 11:00 PM
FrequencyEvery 6 minutes or less at peak
Trains per day276 on weekdays, 223 on Saturdays, 205 on Sundays (Lines 7 and 9 together)
OperatorMMMOCL (same as Line 2A, 2B and 7)
JourneyFare
Pandurang Wadi โ€“ Kashigaonโ‚น10
Dahisar (East) โ€“ Kashigaonโ‚น20
Gundavali โ€“ Pandurang Wadi / Miragaonโ‚น40
Gundavali (Andheri E) โ€“ Kashigaonโ‚น50

Line 9 runs as a continuation of Line 7: trains go straight through from Gundavali to Kashigaon. By road, the same trip takes up to an hour and costs โ‚น350โ€“โ‚น400 by cab or auto.

Interchange stations

Dahisar (East)

โ“‚ Line 2A ยท โ“‚ Line 7

A three-line hub. Line 7 trains continue through; change here for Line 2A towards Borivali (W), Malad (W) and Andheri (W).

Miragaon

โ“‚ Line 10 (proposed)

Planned link to Line 10 towards Gaimukh and Thane, which would connect Mira Road with Line 4.

Kashigaon

Current terminus, serving Kashimira and Mira Road. Phase 2 continues from here to Bhayandar.

Subhash Chandra Bose Stadium

Line 13 (proposed)

Future terminus in Bhayandar, where the proposed Line 13 would continue north to Virar.

Plan your trip

Mira Road to Andheri (E)

  1. Board at Kashigaon, Miragaon or Pandurang Wadi
  2. Stay on the train โ€” it continues as Line 7
  3. Get off at Gundavali; change to Line 1 at WEH for Andheri station or Ghatkopar

Mira Road to Borivali (W) / Andheri (W)

  1. Take Line 9 to Dahisar (East)
  2. Change to Line 2A
  3. Ride towards Borivali (W), Malad (W) or Andheri (W)

Phase 2: Kashigaon to Bhayandar

The second phase extends Line 9 from Kashigaon to Subhash Chandra Bose Stadium in Bhayandar, adding four stations: Sai Baba Nagar, Deepak Hospital (Medtiya Nagar), Shaheed Bhagat Singh Garden and Subhash Chandra Bose Stadium. MMRDA says civil work is about 96% complete. The section still needs safety inspection and certification by the Commissioner of Metro Rail Safety (CMRS) before opening, which is expected around December 2026.

Once Phase 2 opens, Bhayandar residents will be able to ride directly to Andheri (East) on the Red Line, a trip that today depends on crowded Western line trains or congested roads.

Route map

See also: Mumbai Metro map โ€“ all lines

Timeline

  • 2019Construction begins on the Dahisar (East) โ€“ Bhayandar extension of the Red Line.
  • 7 April 2026Phase 1 (Dahisar East โ€“ Kashigaon) inaugurated.
  • 8 April 2026Phase 1 opens to passengers, with through trains from Gundavali via Line 7.
  • October 2026Phase 2 civil work about 96% complete; CMRS inspection pending.

About Metro Line 9

Route explained

Line 9 starts at Dahisar (East), where it meets Line 2A and Line 7, and runs north along the Western Express Highway corridor into Mira Road through Pandurang Wadi, Miragaon and Kashigaon. Phase 2 turns west towards Bhayandar, ending near Subhash Chandra Bose Stadium.

It is the first metro line to serve the Mira-Bhayandar municipal area, one of the fastest-growing suburbs in the region.

Line 9 vs Line 7
Line 9Line 7
RouteDahisar (E) โ€“ BhayandarGundavali โ€“ Dahisar (E)
LengthAbout 11.4 km16.5 km
Stations8 (4 open)14
StatusPartly openFully open
Through trainsYes, Gundavali โ€“ KashigaonYes, Gundavali โ€“ Kashigaon

Both lines form the Red Line. See Line 7 for the stations south of Dahisar.

Project & technical details
ItemDetails
LengthAbout 11.4 km, fully elevated
Stations8
Line colourRed
Project authorityMMRDA
OperatorMMMOCL
Phase 1Dahisar (E) โ€“ Kashigaon, about 5 km, opened April 2026
Phase 2Kashigaon โ€“ Subhash Chandra Bose Stadium, expected December 2026

Frequently asked questions

Is Mumbai Metro Line 9 open?

Partly. The first four stations, from Dahisar (East) to Kashigaon, have been open since 8 April 2026. The remaining four stations to Subhash Chandra Bose Stadium in Bhayandar are expected around December 2026, after safety inspection.

What are the Line 9 timings?

Trains run from about 5:50 AM to 11:00 PM, every six minutes or less at peak times. Timings can change, so check the MMMOCL app before travelling.

What is the fare on Metro Line 9?

Dahisar (East) to Kashigaon costs โ‚น20 and Pandurang Wadi to Kashigaon โ‚น10. A direct trip from Gundavali (Andheri East) to Kashigaon costs โ‚น50.

Can I travel directly from Andheri to Mira Road by metro?

Yes. Line 9 runs as a continuation of Line 7, so trains go directly from Gundavali in Andheri (East) to Kashigaon without changing at Dahisar (East).

How many stations does Line 9 have?

Eight elevated stations in total, of which four are open: Dahisar (East), Pandurang Wadi, Miragaon and Kashigaon.

When will Line 9 reach Bhayandar?

Phase 2 from Kashigaon to Subhash Chandra Bose Stadium is about 96% complete and is expected to open around December 2026, once the Commissioner of Metro Rail Safety approves it.

Where can I change from Line 9 to other lines?

At Dahisar (East) for Line 2A (towards Borivali, Malad and Andheri West). Line 7 trains continue through without a change.

Is Line 9 the same as Line 7?

Both are part of the Red Line. Line 7 runs from Gundavali to Dahisar (East), and Line 9 extends it north to Mira Road and Bhayandar, with through trains on both.

Who operates Line 9?

Maha Mumbai Metro Operation Corporation Ltd (MMMOCL). MMRDA is the project authority.

Other metro lines

Sources: Free Press Journal โ€“ Line 9 fares ยท Lokmat Times โ€“ Phase 1 opens ยท Swarajya โ€“ Phase 2 update ยท Wikipedia โ€“ Red Line