Mumbai Metro Line 12 (Orange Line): Kalyan–Taloja Route, Stations & Status

Mumbai Metro Line 12 Kalyan – Dombivli – Taloja Orange Line

Part of our Mumbai Metro guide — every line, fare, timing and status update in one place.

Mumbai Metro Line 12 is part of the Orange Line and will link Kalyan, Dombivli and Taloja. The 23.6 km elevated line runs from Kalyan APMC to Amandoot (Kharghar) with 19 stations, giving Kalyan – Dombivli its first direct metro link to Navi Mumbai. Work is about 54% complete, and MMRDA is targeting an opening in 2028.

Under construction · about 54% complete

Route

Kalyan APMC – Amandoot (Kharghar)

Length

About 23.6 km (elevated)

Stations

19

Expected

2028

Last checked: October 2026 · Opening dates and fares will be confirmed by MMRDA.

Line 12 route & stations

Under construction · Ⓜ Metro interchange

  • Kalyan APMC Ⓜ Mumbai Metro Line 5 (planned link) · Kalyan West
  • Kalyan
  • Ganesh Nagar
  • Pisavali Gaon
  • Golavali
  • Dombivli MIDC Shil Phata Road
  • Sagaon
  • Sonarpada
  • Manpada (Dombivli East) Ⓜ Line 12A
  • Hedutane Ⓜ Line 14 (planned)
  • Kolegaon
  • Nilaje Gaon
  • Vadavali depot link
  • Bale
  • Waklan
  • Turbhe not the Navi Mumbai station
  • Pisarve Depot
  • Pisarve
  • Amandoot (Kharghar) Ⓜ Navi Mumbai Metro Line 1 · Line 12A

Full station list

#StationStatusInterchange
1Kalyan APMCUnder constructionMumbai Metro Line 5 (planned)
2KalyanUnder construction–
3Ganesh NagarUnder construction–
4Pisavali GaonUnder construction–
5GolavaliUnder construction–
6Dombivli MIDCUnder construction–
7SagaonUnder construction–
8SonarpadaUnder construction–
9Manpada (Dombivli East)Under constructionLine 12A (approved)
10HedutaneUnder constructionLine 14 (planned)
11KolegaonUnder construction–
12Nilaje GaonUnder construction–
13VadavaliUnder construction–
14BaleUnder construction–
15WaklanUnder construction–
16TurbheUnder construction–
17Pisarve DepotUnder construction–
18PisarveUnder construction–
19Amandoot (Kharghar)Under constructionNavi Mumbai Metro Line 1, Line 12A

Station names follow the MMRDA plan and may change before the line opens. Turbhe on this line is a different station from Turbhe in Navi Mumbai.

Current status (October 2026)

  • Progress: about 54% of the work was complete by September 2026, according to MMRDA figures reported in the media.
  • Viaduct: the 100th U-girder was placed near Dombivli MIDC station on Shil Phata Road in December 2025.
  • Contractor: Gawar Constructions is building the viaduct and all 19 stations under a contract worth about ₹2,037 crore.
  • Land: MMRDA is working with the Kalyan-Dombivli, Navi Mumbai and Panvel civic bodies and CIDCO to hand over the remaining land.
  • Target: the original contract deadline was late 2026. MMRDA now expects the line to open in 2028.

Timings & fare

ItemDetails
TimingsTo be announced
FareTo be announced. MMRDA metro lines charge distance-based fares starting at ₹10.
Journey timeAbout 45 minutes from Kalyan to Taloja
AuthorityMMRDA
DepotNilaje, near Dombivli

Interchange stations

Kalyan APMC

Ⓜ Mumbai Metro Line 5 (planned)

Starting point of Line 12 in Kalyan West. Line 12 was planned as a continuation of Mumbai Metro Line 5 (Thane – Bhiwandi – Kalyan), which will link Kalyan to Bhiwandi and Thane.

Manpada (Dombivli East)

Ⓜ Line 12A (approved)

Serves Dombivli East. The new Line 12A will branch off here and run via Kalyan Phata to Amandoot.

Hedutane

Ⓜ Line 14 (planned)

Planned interchange with Line 14, the proposed Vikhroli – Badlapur metro.

Amandoot (Kharghar)

Ⓜ Navi Mumbai Metro Line 1 · Line 12A

End of the line, in Kharghar. Change here to Navi Mumbai Metro Line 1 for Kharghar and CBD Belapur. Line 12A will also end here.

Line 12A: Manpada – Kalyan Phata – Amandoot

Line 12A is a separate, newly approved line that will run alongside Line 12 on a more westerly route. It starts at Manpada (Katai Naka) on Line 12, heads west to Kalyan Phata, then turns south via Dahisar Mori and ends at Amandoot, where it meets Line 12 and Navi Mumbai Metro Line 1.

ItemDetails
Length18.4 km (elevated)
Stations12
Cost₹13,856.37 crore
ApprovalMaharashtra Cabinet Committee on Infrastructure, 27 October 2026
TargetWithin three and a half years, as directed by the Chief Minister
Daily riders (projected)About 4.74 lakh

Line 12A stations

  • Manpada Ⓜ Line 12
  • Katai Naka
  • Kalyan Growth Centre
  • Desai Naka
  • Padle Gaon
  • Kalyan Phata Ⓜ Line 14 (planned)
  • Gotheghar
  • Dahisar Mori
  • Dahisar Gaon
  • Kiravali Gaon
  • Rohinjan
  • Khutari Gaon joins Line 12
  • Amandoot (Kharghar) via Line 12 · Ⓜ Navi Mumbai Metro Line 1

Line 12A station names are based on the approved plan and may change. The project also includes two flyovers along the route, one with four lanes and one with six.

Read our full guide to Mumbai Metro Line 12A for its stations, cost, timeline and the elevated roads planned along the corridor.

Route map

Mumbai Metro Line 12 and Line 12A route map from Kalyan and Manpada to Amandoot (Kharghar)
Line 12 (Kalyan – Taloja) and Line 12A (Manpada – Kalyan Phata – Amandoot). Dashed: under construction · dotted: approved. Schematic, not to scale.

See also: Mumbai Metro map – all lines

Timeline

  • November 2018MMRDA approves the Kalyan – Taloja metro line.
  • July 2019The state government approves the project.
  • September 2019Prime Minister Narendra Modi lays the foundation stone for Line 12, along with Lines 10 and 11.
  • 3 March 2024Groundbreaking ceremony held; Gawar Constructions starts work on the civil contract.
  • December 2025The 100th U-girder is placed near Dombivli MIDC.
  • February 2026MMRDA approves the Line 12A plan.
  • September 2026Work on Line 12 reaches about 54%.
  • 27 October 2026The state cabinet committee approves Line 12A at ₹13,856.37 crore.

About Metro Line 12

Why Line 12 matters

Kalyan, Dombivli and Taloja are among the fastest-growing areas of the Mumbai region, but there is no direct rail link between them. Today, most people travel by road on the busy Shil Phata – Kalyan stretch, which can take an hour or more. Line 12 will cut the trip to about 45 minutes and connect Kalyan – Dombivli with the Navi Mumbai Metro at Amandoot in Kharghar.

Project & technical details

Length: about 23.6 km, fully elevated · Stations: 19 · Gauge: 1,435 mm standard gauge

Cost: ₹5,865 crore · Civil contractor: Gawar Constructions · Depot: Nilaje, about 30 hectares · Authority: MMRDA

Projected ridership: about 2.6 lakh passengers a day by 2031. The depot is planned to hold 24 six-car trains.

Frequently asked questions

Is Mumbai Metro Line 12 open?

Not yet. Line 12 is under construction, and about 54% of the work was complete by September 2026. MMRDA is aiming to open it in 2028. No official opening date has been announced.

What is the route of Metro Line 12?

Line 12 runs from Kalyan APMC through Kalyan, Dombivli MIDC and Manpada (Dombivli East) to Amandoot in Kharghar, Navi Mumbai. The whole 23.6 km route is elevated.

How many stations does Line 12 have?

The current plan has 19 elevated stations, from Kalyan APMC to Amandoot (Kharghar). Station names may change before the line opens.

How long will the journey from Kalyan to Taloja take?

About 45 minutes from end to end, compared with an hour or more by road at busy times.

What is the difference between Line 12 and Line 12A?

Line 12 is the Kalyan – Dombivli – Taloja line that is already being built. Line 12A is a separate 18.4 km line with 12 stations that branches off at Manpada (Katai Naka) and runs via Kalyan Phata to Amandoot. The state government approved Line 12A in October 2026.

Will Line 12 connect to Navi Mumbai Metro and the new airport?

Yes. Amandoot (Kharghar) is the interchange with Navi Mumbai Metro Line 1, which runs to CBD Belapur. A planned extension of that line is expected to reach Navi Mumbai International Airport.

What will the fare be on Line 12?

Fares have not been announced. MMRDA metro lines charge distance-based fares starting at ₹10.

How much does Line 12 cost?

The project is estimated at ₹5,865 crore. The main civil contract for the viaduct and 19 stations is worth about ₹2,037 crore.

Where is the Line 12 depot?

At Nilaje (Nilje) near Dombivli, on about 30 hectares of land. It will connect to the line near Vadavali station.

Other metro lines

Sources: Navbharat Live – 54% complete (Sep 2026) · Oneindia – 100th U-girder (Dec 2025) · The Metro Rail Guy – groundbreaking (Mar 2024) · Free Press Journal – Line 12A approved (Oct 2026) · Wikipedia – Orange Line