Mumbai Metro Line 12A is a new Orange Line corridor that will run parallel to the busy Kalyan – Shil Phata road. The 18.4 km elevated line will start at Manpada (Katai Naka) on Mumbai Metro Line 12, pass through Kalyan Phata and Dahisar Mori, and continue to Khutari near Taloja, linking up with Line 12 and the Navi Mumbai Metro at Amandoot in Kharghar. The Maharashtra government approved the ₹13,856 crore project on 27 October 2026.
Approved · construction yet to begin
Route
Manpada – Kalyan Phata – Khutari
Length
18.4 km (elevated)
Stations
12
Target
About 3.5 years
Last checked: October 2026 · Timelines and station names may change as the project moves ahead.
Line 12A route & stations
Approved · Ⓜ Metro interchange
- Manpada Ⓜ Line 12 · Dombivli East
- Katai Naka Ⓜ Line 14 (planned) · bullet train link
- Kalyan Growth Centre
- Desai Naka
- Padle Gaon
- Kalyan Phata Ⓜ Line 14 (planned) · Shil Phata
- Gotheghar
- Dahisar Mori
- Dahisar Gaon
- Kiravali Gaon
- Rohinjan
- Khutari Gaon joins Line 12
- Amandoot (Kharghar) end point via Line 12 · Ⓜ Navi Mumbai Metro Line 1
Full station list
| # | Station | Status | Interchange |
|---|---|---|---|
| 1 | Manpada | Approved | Line 12 |
| 2 | Katai Naka | Approved | Line 14 (planned) |
| 3 | Kalyan Growth Centre | Approved | – |
| 4 | Desai Naka | Approved | – |
| 5 | Padle Gaon | Approved | – |
| 6 | Kalyan Phata | Approved | Line 14 (planned) |
| 7 | Gotheghar | Approved | – |
| 8 | Dahisar Mori | Approved | – |
| 9 | Dahisar Gaon | Approved | – |
| 10 | Kiravali Gaon | Approved | – |
| 11 | Rohinjan | Approved | – |
| 12 | Khutari Gaon | Approved | – |
| 13 | Amandoot (Kharghar) | Via Line 12 | Navi Mumbai Metro Line 1, Line 12 |
After Khutari Gaon, Line 12A merges with the Line 12 corridor and continues to Amandoot in Kharghar, the interchange with Navi Mumbai Metro Line 1. Station names are based on the approved plan and may change; some reports spell them differently (for example Padle or Padelagaon, and Khutari or Khutare).
Current status (October 2026)
- Approval: the Maharashtra Cabinet Committee on Infrastructure approved Line 12A on 27 October 2026 at an estimated ₹13,856.37 crore.
- Deadline: Chief Minister Devendra Fadnavis has asked MMRDA to complete the project within three and a half years.
- Earlier approval: MMRDA gave administrative approval for the line in February 2026 at ₹8,414.53 crore.
- Planning authority: MMRDA has been named the special planning authority for the metro corridor and the elevated roads built with it.
- Funding: the plan combines MMRDA funds, interest-free loans from the state government and borrowing from financial institutions. The state has also handed government land along the route to MMRDA to help raise money.
- Next: land acquisition, tenders and the appointment of contractors.
Key facts
| Item | Details |
|---|---|
| Line | Line 12A (Orange Line) |
| Route | Manpada (Katai Naka) – Kalyan Phata – Dahisar Mori – Khutari, then via Line 12 to Amandoot |
| Length | 18.4 km, fully elevated (including the depot link) |
| Stations | 12 |
| Cost | ₹13,856.37 crore |
| Daily riders (projected) | About 4.74 lakh |
| Authority | MMRDA |
| Depot | Linked to the Nilje depot of Line 12 |
| Timings & fare | To be announced |
Interchange stations
Manpada (Katai Naka)
Starting point in Dombivli East. Change here to Mumbai Metro Line 12 for Kalyan, Dombivli MIDC and Pisarve. A link to the proposed Thane bullet train station is also planned from this area.
Katai Naka – Kalyan Phata
Line 12A will share this section, including its stations, with the planned Line 14 between Kanjurmarg and Badlapur.
Amandoot (Kharghar)
After joining the Line 12 corridor near Khutari, trains will reach Amandoot, where riders can change to Navi Mumbai Metro Line 1 for Kharghar and CBD Belapur.
Line 12 vs Line 12A
| Item | Details |
|---|---|
| Line 12 | Kalyan APMC – Dombivli MIDC – Manpada – Amandoot · 23.6 km · 19 stations · under construction, target 2028 |
| Line 12A | Manpada – Kalyan Phata – Dahisar Mori – Khutari · 18.4 km · 12 stations · approved in October 2026 |
| Where they meet | Manpada (Katai Naka) at the north end and the Khutari – Amandoot stretch at the south end |
Together, the two lines form a loop. Line 12 serves Dombivli MIDC, Hedutane and Pisarve, while Line 12A runs along the Kalyan – Shil Phata road through Kalyan Phata and Dahisar Mori. Read our full guide to Mumbai Metro Line 12.
Elevated roads on the same corridor
Line 12A is part of an integrated plan to ease traffic on the Kalyan – Shil Phata road. Along with the metro, the approved project includes a 6.93 km four-lane flyover and an 8.69 km six-lane flyover. A double-decker road and metro structure has also been proposed between Kalyan Phata and Rajnoli, linking with the Mahape flyover.
Elevated road details are based on official announcements and news reports and may be revised during detailed design.
Route map

See also: Mumbai Metro map – all lines
Timeline
- February 2026MMRDA gives administrative approval for Line 12A at ₹8,414.53 crore.
- 27 October 2026The Maharashtra Cabinet Committee on Infrastructure approves Line 12A at ₹13,856.37 crore and sets a three-and-a-half-year deadline.
- NextLand acquisition, tenders and the start of construction.
About Metro Line 12A
Why Line 12A matters
The Kalyan – Shil Phata road is one of the most congested roads in the Mumbai region, used daily by commuters heading from Kalyan and Dombivli to Navi Mumbai, Thane and the Taloja and Mahape industrial areas. Line 12A gives this stretch its own metro, and MMRDA expects it to cut travel times by 40–50% compared with the road.
Future extensions
Local leaders have said Line 12A could later be extended to Kalwa, Diva and Mumbra. These extensions have not been approved yet.
Project & technical details
Length: 18.4 km, fully elevated · Stations: 12 · Gauge: 1,435 mm standard gauge
Cost: ₹13,856.37 crore · Daily riders: about 4.74 lakh · Authority: MMRDA
Frequently asked questions
What is Mumbai Metro Line 12A?
Line 12A is an approved 18.4 km elevated metro line in the Kalyan – Dombivli area. It will run from Manpada (Katai Naka) in Dombivli East via Kalyan Phata and Dahisar Mori to Khutari near Taloja, and link up with Line 12 and Navi Mumbai Metro Line 1 at Amandoot in Kharghar.
Is Metro Line 12A approved?
Yes. MMRDA gave administrative approval in February 2026, and the Maharashtra Cabinet Committee on Infrastructure, chaired by Chief Minister Devendra Fadnavis, approved the project on 27 October 2026.
How many stations will Line 12A have?
12 elevated stations: Manpada, Katai Naka, Kalyan Growth Centre, Desai Naka, Padle Gaon, Kalyan Phata, Gotheghar, Dahisar Mori, Dahisar Gaon, Kiravali Gaon, Rohinjan and Khutari Gaon.
When will Line 12A be ready?
The Chief Minister has asked for the project to be finished within three and a half years of approval, which points to around 2030. Construction has not started yet, so no opening date has been announced.
How much will Line 12A cost?
The project approved in October 2026 is estimated at ₹13,856.37 crore. The earlier administrative approval in February 2026 was for ₹8,414.53 crore.
How is Line 12A different from Line 12?
Line 12 runs from Kalyan APMC through Dombivli MIDC and Manpada to Amandoot and is already under construction. Line 12A branches off at Manpada and takes a more westerly route along the Kalyan – Shil Phata road via Kalyan Phata, then rejoins the Line 12 corridor near Khutari before Amandoot.
Will Line 12A connect with other metro lines?
Yes. It will connect with Line 12 at Manpada, share its Katai Naka – Kalyan Phata section with the planned Line 14 (Kanjurmarg – Badlapur), and reach Navi Mumbai Metro Line 1 at Amandoot in Kharghar.
How many people will use Line 12A?
About 4.74 lakh passengers a day are expected once the line is running.
Who will build Line 12A?
MMRDA will build the line and has been named the special planning authority for the metro corridor and the elevated roads that come with it. A construction contractor has not been appointed yet.
Other metro lines