Mumbai Metro Line 4 (Green Line): Route, Stations, Status & Opening Date

Mumbai Metro Line 4 & 4A

Part of our Mumbai Metro guide — every line, fare, timing and status update in one place.

Mumbai Metro Line 4 (Green Line) is a 32.32 km elevated metro line from Wadala to Kasarvadavali in Thane, running along the Eastern Express Highway through Ghatkopar, Vikhroli, Bhandup and Mulund. Together with Line 4A to Gaimukh, it will be the main metro link between Thane and Mumbai. The first 10.5 km, from Gaimukh to Cadbury Junction, has finished trials and is now expected to open in December 2026.

Under construction · Phase 1 trials done

Length

32.32 km

Stations

30 (elevated)

First section

Gaimukh – Cadbury Jn

Expected

December 2026

Last checked: 29 October 2026 · Opening dates and fares will be confirmed by MMRDA and MMMOCL.

Line 4 route & stations

Phase 1 – trials Under construction · Ⓜ Metro interchange

  • Gaimukh via Line 4A · Phase 1
  • Kasarvadavali Ⓜ Line 4A · Phase 1
  • Kapurbawdi Ⓜ Line 5 · Phase 1
  • Cadbury Junction end of Phase 1
  • Teen Haath Naka Thane
  • Mulund Naka
  • Bhandup
  • Gandhi Nagar (Kanjurmarg) Ⓜ Line 6
  • Vikhroli
  • Laxmi Nagar Ⓜ Line 1 (Ghatkopar)
  • Siddharth Colony Ⓜ Line 2B
  • Bhakti Park (Wadala) Monorail · Line 11 (proposed)

Key stops shown. Full list of all 30 stations below.

Full station list

#StationStatusInterchange
1KasarvadavaliPhase 1 – trialsLine 4A towards Gaimukh
2Vijay GardenPhase 1 – trials–
3DongripadaPhase 1 – trials–
4Tikuji-ni-wadiPhase 1 – trials–
5ManpadaPhase 1 – trials–
6KapurbawdiPhase 1 – trialsLine 5 (under construction)
7MajiwadaPhase 1 – trials–
8Cadbury JunctionPhase 1 – trials–
9Mahapalika MargUnder construction–
10RTO ThaneUnder construction–
11Teen Haath NakaUnder construction–
12Mulund NakaUnder construction–
13Mulund Fire StationUnder construction–
14SonapurUnder construction–
15ShangrilaUnder construction–
16BhandupUnder construction–
17Bhandup MahapalikaUnder construction–
18Naval HousingUnder construction–
19Gandhi Nagar (Kanjurmarg)Under constructionLine 6 (under construction)
20Surya NagarUnder construction–
21VikhroliUnder construction–
22Godrej CompanyUnder construction–
23Shreyas CinemaUnder construction–
24Laxmi NagarUnder constructionLine 1 (Ghatkopar)
25Pant NagarUnder construction–
26Garodia NagarUnder constructionLine 8 (proposed)
27Siddharth ColonyUnder constructionLine 2B
28Anik Nagar Bus DepotUnder construction–
29Wadala Truck TerminalUnder construction–
30Bhakti Park (Wadala)Under constructionMonorail · Line 11 (proposed)

Phase 1 also includes the two Line 4A stations north of Kasarvadavali, Gowniwada and Gaimukh, making ten stations from Gaimukh to Cadbury Junction. See the Line 4A page.

Current status (October 2026)

  • Phase 1: Gaimukh – Cadbury Junction (about 10.5 km, 10 stations including Line 4A) has finished trial runs, which began between Gaimukh and Vijay Garden in September 2025 and later covered the whole stretch. On 26 October 2026, Transport Minister Pratap Sarnaik said this first phase will open in December 2026, later than the earlier Diwali target. Final safety approval for passenger services is still awaited.
  • Safety testing: RDSO certified the trains, track and signalling on 2 June 2026. In August 2026 the Commissioner of Metro Rail Safety (CMRS) cleared the rolling stock and inspected the temporary pit line at Gaimukh.
  • Trains: on 14 October 2026, Alstom unveiled the first of the line’s own 39 driverless six-car Metropolis trains at its Sri City factory, built in 14 months. They run at up to 80 km/h and have wheelchair spaces and bicycle racks. Until enough of these trains are delivered and tested, the first services are expected to use interim trains from the Charkop depot (used on Lines 2A, 7 and 9).
  • Depot: the Mogharpada depot on Ghodbunder Road is not ready; trains will be stabled and serviced at Gaimukh until it is.
  • Rest of the line: Cadbury Junction to Wadala is still under construction, with no firm opening dates.

Timings & fare

ItemDetails
TimingsTo be announced
FareTo be announced. MMMOCL lines charge distance-based fares starting at ₹10.
OperatorMMMOCL (Maha Mumbai Metro Operation Corporation)
TrainsSix-car trains; interim rakes from Charkop depot at launch

Line 4 and Line 4A will run as one Green Line service from Gaimukh. In future, the proposed Line 10 will continue from Gaimukh towards Mira Road, linking with Line 9.

Interchange stations

Kasarvadavali

Ⓜ Line 4A

The original northern end of Line 4 on Ghodbunder Road. Trains continue 2.88 km to Gaimukh on Line 4A.

Kapurbawdi

Ⓜ Line 5 (under construction)

Planned interchange with Line 5 towards Bhiwandi and Kalyan, and close to Viviana and Korum malls.

Gandhi Nagar (Kanjurmarg)

Ⓜ Line 6

Interchange with Line 6 (Pink Line) towards Powai, JVLR and Jogeshwari.

Laxmi Nagar (Ghatkopar)

Ⓜ Line 1

Connection towards Line 1 (Blue Line) for Andheri and Versova.

Siddharth Colony

Ⓜ Line 2B

Interchange with Line 2B (Yellow Line) towards Chembur, Kurla, BKC and Mandale.

Bhakti Park (Wadala)

Monorail · Line 11 (proposed)

Southern terminus, next to the Bhakti Park Monorail station. The proposed Line 11 would continue to south Mumbai.

Plan your trip

Ghodbunder Road to Cadbury Junction (Phase 1)

  1. Board at Gaimukh, Kasarvadavali or any Ghodbunder Road station
  2. Ride south through Manpada and Kapurbawdi
  3. Get off at Cadbury Junction or Majiwada for central Thane

Thane to Ghatkopar or Wadala (full line)

  1. Board at any Thane station
  2. Change at Gandhi Nagar for Line 6, or at Laxmi Nagar towards Line 1
  3. Continue to Siddharth Colony for Line 2B or to Wadala for the Monorail

The full-line trip will only be possible once the southern sections open.

Route map

See also: Mumbai Metro map – all lines

Timeline

  • 2016Line 4 approved by the state; foundation stone laid in December.
  • October 2018Construction begins.
  • November 2020KfW signs a €545 million loan for the project.
  • March 2022Original train order with Alstom cancelled.
  • March 2023Bombay High Court dismisses petitions against the alignment.
  • December 2023Amar Mahal Junction and Suman Nagar stations dropped.
  • February 2025L&T–Alstom awarded the contract for 39 trains and signalling.
  • September 2025Trial runs begin between Gaimukh and Vijay Garden.
  • February 2026Parapet collapse at Mulund delays safety work by about two months.
  • June – August 2026RDSO certification; CMRS clears the trains and inspects the Gaimukh pit line.
  • October 2026Alstom unveils the first of 39 driverless trains; the Transport Minister says Phase 1 will open in December 2026.

About Metro Line 4

Route explained

From Kasarvadavali, Line 4 runs south along Ghodbunder Road to Cadbury Junction, through Thane to Mulund, and then along LBS Marg through Bhandup, Kanjurmarg, Vikhroli and Ghatkopar. It ends at Bhakti Park near the Wadala Truck Terminal. Line 4A adds two stations north to Gaimukh.

Why Line 4 matters

Thane to Mumbai traffic today relies on the Central Railway locals and the congested Eastern Express Highway. Line 4 gives Ghodbunder Road and LBS Marg their first rail link, with connections to four other metro lines and the Monorail.

Project & technical details

Length: 32.32 km, fully elevated · Stations: 30 · Gauge: 1,435 mm standard gauge · Power: 25 kV AC overhead · Speed: up to 90 km/h

Cost: about ₹14,549 crore · Funding: includes a KfW (Germany) loan · Depot: Mogharpada, Thane · Trains: 39 driverless six-car Alstom Metropolis trains (L&T–Alstom contract) · Authority: MMRDA

Frequently asked questions

Is Mumbai Metro Line 4 open?

Not yet. The first section, about 10.5 km from Gaimukh to Cadbury Junction in Thane, has finished trial runs and safety testing. The state government now expects it to open in December 2026, subject to final safety approval. No exact opening date has been announced yet.

What is the route of Metro Line 4?

Line 4 (Green Line) runs from Wadala in central Mumbai to Kasarvadavali on Ghodbunder Road in Thane, along the Eastern Express Highway and LBS Marg. Line 4A extends it 2.88 km further to Gaimukh.

How many stations does Line 4 have?

30 elevated stations between Kasarvadavali and Bhakti Park (Wadala). Two stations in the original plan, Amar Mahal Junction and Suman Nagar, were dropped by MMRDA.

Which stations open first on Line 4?

Phase 1 covers ten stations: Gaimukh, Gowniwada, Kasarvadavali, Vijay Garden, Dongripada, Tikuji-ni-wadi, Manpada, Kapurbawdi, Majiwada and Cadbury Junction. The first two are on Line 4A.

Where can I change from Line 4 to other metro lines?

Planned interchanges include Line 6 at Gandhi Nagar (Kanjurmarg), Line 1 near Ghatkopar, Line 2B at Siddharth Colony, the Monorail at Bhakti Park (Wadala) and Line 5 at Kapurbawdi. Most of these will only work once the relevant sections open.

What will the fare be on Line 4?

Fares have not been announced. Other MMMOCL-run lines charge distance-based fares starting at ₹10.

When will Line 4 reach Wadala?

The line will open in stages southwards from Thane. MMRDA has not announced firm dates for the Cadbury Junction – Gandhi Nagar and Gandhi Nagar – Wadala sections.

Who operates Line 4?

MMRDA is building the line. Safety clearances for the first section have been issued to MMRDA and Maha Mumbai Metro Operation Corporation (MMMOCL), which will run the trains.

What trains will run on Metro Line 4?

Line 4 and 4A will use 39 driverless six-car Metropolis trains from Alstom, supplied under an L&T–Alstom contract. The first train was unveiled on 14 October 2026. Until enough of them are delivered and tested, the first services are expected to use interim trains from the Charkop depot.

Why has Line 4 been delayed?

The line was first due in 2022. Delays came from land and court issues, a cancelled train order, and in 2026 a fatal parapet collapse at Mulund that held up safety work by about two months. The Mogharpada depot is also not ready, so trains will be maintained at a temporary pit line at Gaimukh.

Other metro lines

Sources: Free Press Journal – December 2026 opening (Oct 2026) · Alstom – first Line 4 & 4A train (Oct 2026) · Free Press Journal – trials resume (Sep 2026) · Curly Tales – rolling stock clearance (Aug 2026) · Free Press Journal – CMRS pit-line inspection · Swarajya – revised target · Wikipedia – Green Line