Mumbai Infrastructure Projects

Every major metro line, road, tunnel, sea link, rail line and airport project in Mumbai, Thane and Navi Mumbai, with its status and expected opening date. Search by your area or filter by type.

Upcoming9 projects6 under construction ยท 2 partly open ยท 1 approved
Completed5 openEarliest opened in 2014
Opening nextDec 2026Metro Line 4, 4A & 5
Due by 20285 of 9upcoming projects target 2028 or earlier

Upcoming projects

Mumbai Metro Line 2B (Yellow) Metro
Partly open

Mumbai Metro Line 2B (Yellow)

DN Nagar โ€“ Mandale; 6 of 20 stations open

DN Nagar, Bandra, BKC, Kurla, Chembur, Mankhurd, Mandale

Expected: Not announced

View details โ†’
Mumbai Metro Line 9 (Red) Metro
Partly open

Mumbai Metro Line 9 (Red)

Dahisar East โ€“ Mira-Bhayandar; 4 of 8 stations open

Dahisar East, Mira Road, Bhayandar, Kashigaon

Expected: Not announced

View details โ†’
Mumbai Metro Line 4 (Green) Metro
Under construction

Mumbai Metro Line 4 (Green)

32.3 km Wadala โ€“ Kasarvadavali, 30 stations

Wadala, Ghatkopar, Mulund, Thane, Kasarvadavali

Expected: Dec 2026 (first section)

View details โ†’
Mumbai Metro Line 4A (Green) Metro
Under construction

Mumbai Metro Line 4A (Green)

2.9 km Gaimukh extension of Line 4

Kasarvadavali, Gaimukh, Thane

Expected: Dec 2026

View details โ†’
Mumbai Metro Line 5 (Orange) Metro
Under construction

Mumbai Metro Line 5 (Orange)

Thane โ€“ Bhiwandi โ€“ Kalyan line, Phase 1 near completion

Thane, Kapurbawdi, Bhiwandi, Kalyan

Expected: Dec 2026 (Phase 1)

View details โ†’
Mumbai Metro Line 6 (Pink) Metro
Under construction

Mumbai Metro Line 6 (Pink)

15.3 km eastโ€“west line, 13 stations

Lokhandwala, Jogeshwari, SEEPZ, Powai, Vikhroli

Expected: Early 2027 (partial)

View details โ†’
Mumbai Metro Line 7A (Red) Metro
Under construction

Mumbai Metro Line 7A (Red)

3.4 km link from Gundavali to Mumbai Airport T2

Andheri East, Gundavali, Airport T2

Expected: Not announced

View details โ†’
Mumbai Metro Line 12 (Orange) Metro
Under construction

Mumbai Metro Line 12 (Orange)

23.6 km Kalyan APMC โ€“ Amandoot, 19 stations

Kalyan, Dombivli, Taloja, Kharghar

Expected: 2028

View details โ†’
Mumbai Metro Line 12A Metro
Approved

Mumbai Metro Line 12A

18.4 km Manpada โ€“ Kalyan Phata โ€“ Khutari, 12 stations

Dombivli, Manpada, Kalyan Phata, Khutari, Kharghar

Expected: About 2030

View details โ†’
Mumbai Metro Line 1 (Blue) Metro
Open

Mumbai Metro Line 1 (Blue)

11.4 km elevated line, 12 stations

Versova, Andheri, Ghatkopar

Opened 2014

View details โ†’
Mumbai Metro Line 2A (Yellow) Metro
Open

Mumbai Metro Line 2A (Yellow)

Dahisar East โ€“ Andheri West along Link Road, 17 stations

Dahisar, Borivali, Kandivali, Malad, Goregaon, Andheri West

Opened 2023

View details โ†’
Mumbai Metro Line 3 (Aqua) Metro
Open

Mumbai Metro Line 3 (Aqua)

Underground line, Cuffe Parade โ€“ Aarey JVLR, 27 stations

Cuffe Parade, Churchgate, Worli, BKC, Airport, Aarey

Fully open 2025

View details โ†’
Mumbai Metro Line 7 (Red) Metro
Open

Mumbai Metro Line 7 (Red)

Dahisar East โ€“ Gundavali along Western Express Highway, 14 stations

Dahisar East, Borivali, Kandivali, Goregaon, Andheri East

Opened 2023

View details โ†’
Navi Mumbai Metro Line 1 Metro
Open

Navi Mumbai Metro Line 1

11.1 km Belapur โ€“ Pendhar line, 11 stations

Belapur, Kharghar, Taloja, Pendhar

Opened 2023

View details โ†’

Mumbai is in the middle of its biggest building boom. New metro lines, sea links, tunnels, rail lines and a second airport will change how the city moves over the next few years. This page lists every major upcoming infrastructure project in Mumbai, with its route, current status and expected opening date, all in one place.

Updated monthly ยท targets as announced

Metro lines being built

8 (and 2 approved)

Major road projects

7 tunnels, links & sea routes

Opening next

Metro 4/4A, 9, 5 (late 2026)

Big milestone year

2028

Last checked: October 2026 ยท Opening dates are official targets and may change.

Open Partly open Under construction Approved Planned

Metro lines

Mumbai already has four fully running metro lines (1, 2A, 3 and 7), plus open sections of Lines 2B and 9. These are the lines that are under construction or approved, from the closest to opening to the furthest away. See our Mumbai Metro guide and Mumbai Metro map for running lines, fares and timings.

LineRouteStatusExpected
Line 2B (Yellow)D.N. Nagar โ€“ BKC โ€“ Kurla โ€“ Chembur โ€“ MandalePartly openFull line by about 2028
Line 4 & Line 4A (Green)Wadala โ€“ Ghatkopar โ€“ Thane โ€“ GaimukhUnder constructionGaimukh โ€“ Cadbury Junction by Dec 2026; rest by about 2028
Line 5 (Orange)Thane โ€“ Bhiwandi โ€“ KalyanUnder constructionPhase 1 (Kapurbawdi โ€“ Dhamankar Naka) around Dec 2026
Line 6 (Pink)Swami Samarth Nagar โ€“ JVLR โ€“ VikhroliUnder constructionIn stages from 2027
Line 7A (Red)Gundavali โ€“ Airport Terminal 2Under construction2027
Line 9 (Red)Dahisar (E) โ€“ Mira Road โ€“ BhayandarPartly openRest of the line around Dec 2026
Line 12 (Orange)Kalyan APMC โ€“ Dombivli โ€“ Amandoot (Kharghar)Under constructionAbout 54% done; target 2028
Line 12A (Orange)Manpada โ€“ Kalyan Phata โ€“ AmandootApprovedApproved Oct 2026; about 3.5 years to build
Line 8 (Gold)Mumbai Airport โ€“ Navi Mumbai AirportApprovedApproved Jan 2025; builder yet to be appointed
Line 10 (Green)Gaimukh โ€“ Mira RoadPlannedAwaiting approvals
Line 11 (Green)Wadala โ€“ CSMTPlannedNot yet scheduled
Line 13 (Purple)Mira-Bhayandar โ€“ VirarPlannedNot yet scheduled
Line 14 (Magenta)Vikhroli โ€“ Kanjurmarg โ€“ BadlapurPlannedNot yet scheduled

Roads, tunnels & sea links

These projects aim to ease Mumbai’s worst traffic bottlenecks, especially the northโ€“south crawl along the western suburbs and the eastโ€“west crossings over the hills of Sanjay Gandhi National Park.

ProjectWhat it isStatusExpected
Coastal Road NorthVersova โ€“ Dahisar โ€“ Bhayandar, extending the Mumbai Coastal Road north along the western coastUnder constructionDec 2028 (Mar 2029 at the latest)
Versova โ€“ Bandra Sea LinkAbout 17 km sea bridge off the western coast, linking to the Bandraโ€“Worli Sea LinkUnder constructionAbout 31% done (May 2026); target May 2028
Goregaon โ€“ Mulund Link Road (GMLR)12.2 km eastโ€“west road with twin tunnels under Sanjay Gandhi National ParkUnder constructionFlyover about 48%, tunnels about 18% (Mar 2026); target 2028
Thane โ€“ Borivali twin tunnel11.8 km tunnels under Sanjay Gandhi National Park from Ghodbunder Road to the Western Express HighwayUnder constructionTarget 2028; cuts the trip from over an hour to about 15 minutes
Orange Gate โ€“ Marine Drive tunnelAbout 10 km link, mostly underground, from the Eastern Freeway to the Coastal RoadUnder constructionTunnelling began Dec 2025; target Dec 2028
Sewri โ€“ Worli elevated connector4.5 km elevated road linking Atal Setu (MTHL) at Sewri to Worli, near the Coastal Road and Bandraโ€“Worli Sea LinkUnder constructionOpening pushed to early 2027
Uttan โ€“ Virar Sea Link55 km sea route from Uttan (Bhayandar) to Virar, linking with the Delhiโ€“Mumbai ExpresswayPlannedAlignment being finalised; cost over โ‚น58,000 crore

Rail projects

More tracks mean more local trains and fewer delays. These are the main rail projects in the Mumbai region, alongside the bullet train. For today’s local train lines and routes, see our Mumbai local train guide.

ProjectWhat it isStatusExpected
Mumbai โ€“ Ahmedabad bullet train508 km high-speed line; Maharashtra stations at BKC (underground), Thane, Virar and BoisarUnder constructionFirst section (Surat โ€“ Vapi, Gujarat) targeted for Aug 2027
Kalyan โ€“ Badlapur 3rd & 4th linesExtra tracks so more local trains can run on the Central lineUnder constructionAbout 52% done (Jul 2026); target 2028
Borivali โ€“ Virar 5th & 6th linesExtra tracks on the Western line north of BorivaliUnder constructionAbout 30% done (Jul 2026); target 2029
Panvel โ€“ Karjat suburban corridor29.6 km new line with stations at Panvel, Chikhale, Poyanje, Chouk and KarjatUnder constructionBridges and tunnel digging complete; opening date not yet announced

Airport & housing

ProjectWhat it isStatusLatest
Navi Mumbai International AirportMumbai’s second airport at Ulwe, Navi MumbaiOpenFlights since 25 Dec 2025; a larger second terminal is being planned
Dharavi redevelopmentRebuilding of Dharavi with new homes for eligible residentsUnder constructionFirst 10,000 rehab homes promised within about 18 months (Jul 2026)

Which projects help my area?

If you live or are planning to buy or rent in one of these areas, these are the projects to watch.

AreaProjects nearby
Western suburbs (Andheri โ€“ Dahisar โ€“ Bhayandar)Coastal Road North, Versova โ€“ Bandra Sea Link, GMLR, Thane โ€“ Borivali tunnel, Line 9, Line 7A, Borivali โ€“ Virar rail lines
Thane & Ghodbunder RoadLine 4 & Line 4A, Line 5, Thane โ€“ Borivali tunnel, bullet train (Thane station)
Kalyan, Dombivli & BadlapurLine 5, Line 12, Line 12A, Kalyan โ€“ Badlapur 3rd & 4th lines
Navi Mumbai & PanvelNavi Mumbai Airport, Line 12 and Line 12A (at Amandoot), Line 8, Panvel โ€“ Karjat corridor
Central suburbs (Ghatkopar, Vikhroli, Chembur)Line 4, Line 6, Line 2B, GMLR (Mulund end)
South Mumbai, Worli & BKCSewri โ€“ Worli connector, Orange Gate โ€“ Marine Drive tunnel, Line 2B, bullet train (BKC)

What opens when

  • Late 2026Metro Line 4/Line 4A (Gaimukh โ€“ Cadbury Junction), rest of Line 9 and Phase 1 of Line 5 are all targeted around December.
  • 2027Sewri โ€“ Worli connector, Metro Line 7A and the first stretches of Line 6; the first bullet train section opens in Gujarat.
  • 2028Big year for roads: GMLR, Thane โ€“ Borivali tunnel, Orange Gate โ€“ Marine Drive tunnel, Versova โ€“ Bandra Sea Link and Coastal Road North; also Line 12, the full Line 2B and Line 4, and the Kalyan โ€“ Badlapur rail lines.

Big projects in Mumbai often run late, so treat these as current targets, not promises. We update them as soon as new dates are announced.

Recently opened

  • Mumbai Trans Harbour Link (Atal Setu), Sewri โ€“ Nhava Sheva, opened in January 2024.
  • Mumbai Coastal Road (south), Marine Drive โ€“ Worli, fully opened in stages through 2024โ€“25.
  • Metro Line 3 (Aqua), Cuffe Parade โ€“ BKC โ€“ Aarey, fully open since October 2025.
  • Navi Mumbai International Airport, commercial flights from 25 December 2025.
  • Mumbai โ€“ Pune Expressway “missing link” near Lonavala (13.3 km), opened on 1 May 2026, saving about 20โ€“30 minutes.

Frequently asked questions

Which big infrastructure projects are coming up in Mumbai?

The main ones are new metro lines (2B, 4, 4A, 5, 6, 7A, 9, 12 and 12A), the Coastal Road extension to Dahisar and Bhayandar, the Versova โ€“ Bandra Sea Link, the Goregaon โ€“ Mulund Link Road, the Thane โ€“ Borivali tunnel, the Orange Gate โ€“ Marine Drive tunnel, the Sewri โ€“ Worli connector and the Mumbai โ€“ Ahmedabad bullet train.

Which projects will open next?

Several metro sections are targeted for late 2026: Line 4 and 4A between Gaimukh and Cadbury Junction in Thane, the rest of Line 9 to Bhayandar, and Phase 1 of Line 5 from Thane to Bhiwandi. The Sewri โ€“ Worli connector is expected in early 2027.

When will the Thane โ€“ Borivali tunnel open?

It is targeted for 2028. The 11.8 km twin tunnels will run under Sanjay Gandhi National Park and cut the Thane โ€“ Borivali drive from over an hour to about 15 minutes.

When will the Coastal Road reach Dahisar and Bhayandar?

The northern extension from Versova to Dahisar and Bhayandar is targeted for December 2028, with March 2029 as the latest date.

When will the bullet train reach Mumbai?

The first section, between Surat and Vapi in Gujarat, is targeted for August 2027. The Mumbai end, with an underground station at BKC, will open later; no date has been announced yet.

Is Navi Mumbai Airport open?

Yes. Navi Mumbai International Airport started commercial flights on 25 December 2025. A larger second terminal for international flights is being planned.

Which areas will benefit the most?

The western suburbs gain the most road projects (Coastal Road North, the sea link, GMLR and the Thane โ€“ Borivali tunnel), while Thane, Kalyan โ€“ Dombivli and Navi Mumbai gain several new metro lines.

How often is this page updated?

We review it whenever an important project reaches a milestone, and at least once a month. Dates are official targets and often move, so check the “last checked” date at the top.

Sources: Construction World โ€“ Coastal Road (Aug 2026) ยท Construction World โ€“ Versovaโ€“Bandra Sea Link (Jul 2026) ยท Swarajya โ€“ GMLR (Mar 2026) ยท ThePrint โ€“ Orange Gate tunnel & Thaneโ€“Borivali tunnel ยท PropNewsTime โ€“ Sewriโ€“Worli connector (Jul 2026) ยท Free Press Journal โ€“ Uttanโ€“Virar Sea Link (Jul 2026) ยท India TV โ€“ bullet train (Aug 2026) ยท Free Press Journal โ€“ rail lines (Aug 2026) ยท Wikipedia โ€“ Panvelโ€“Karjat corridor ยท AIR News โ€“ Navi Mumbai Airport ยท Business Today โ€“ Dharavi (Jul 2026) ยท AIR News โ€“ Mumbaiโ€“Pune missing link