Mumbai Metro Line 9 (Red Line) is an elevated metro line extending Line 7 north from Dahisar (East) to Mira Road and Bhayandar. The first four stations, from Dahisar (East) to Kashigaon, opened on 8 April 2026, with direct trains from Gundavali in Andheri (East). The remaining four stations to Bhayandar are expected around December 2026.
Partly open ยท Dahisar (East) โ Kashigaon
Timings
5:50 AM โ 11:00 PM
Frequency
Under 6 min at peak
Fare
โน10 โ โน20 (โน50 from Gundavali)
Stations open
4 of 8
Last checked: October 2026 ยท Timings and fares can change โ confirm on MMMOCL’s app or website.
Line 9 route & stations
Operational Under construction ยท โ Metro interchange
- Dahisar (East) โ Line 2A ยท โ Line 7
- Pandurang Wadi
- Miragaon โ Line 10 (proposed)
- Kashigaon current terminus
- Sai Baba Nagar
- Deepak Hospital (Medtiya Nagar)
- Shaheed Bhagat Singh Garden
- Subhash Chandra Bose Stadium Bhayandar ยท Line 13 (proposed)
Full station list
| # | Station | Status | Interchange |
|---|---|---|---|
| 1 | Dahisar (East) | Operational | Line 2A, Line 7 |
| 2 | Pandurang Wadi | Operational | โ |
| 3 | Miragaon | Operational | Line 10 โ proposed |
| 4 | Kashigaon | Operational | โ |
| 5 | Sai Baba Nagar | Under construction | โ |
| 6 | Deepak Hospital (Medtiya Nagar) | Under construction | โ |
| 7 | Shaheed Bhagat Singh Garden | Under construction | โ |
| 8 | Subhash Chandra Bose Stadium | Under construction | Line 13 โ proposed |
Timings & fare
| Item | Details |
|---|---|
| First train | Around 5:50 AM |
| Last train | Around 11:00 PM |
| Frequency | Every 6 minutes or less at peak |
| Trains per day | 276 on weekdays, 223 on Saturdays, 205 on Sundays (Lines 7 and 9 together) |
| Operator | MMMOCL (same as Line 2A, 2B and 7) |
| Journey | Fare |
|---|---|
| Pandurang Wadi โ Kashigaon | โน10 |
| Dahisar (East) โ Kashigaon | โน20 |
| Gundavali โ Pandurang Wadi / Miragaon | โน40 |
| Gundavali (Andheri E) โ Kashigaon | โน50 |
Line 9 runs as a continuation of Line 7: trains go straight through from Gundavali to Kashigaon. By road, the same trip takes up to an hour and costs โน350โโน400 by cab or auto.
Interchange stations
Miragaon
Planned link to Line 10 towards Gaimukh and Thane, which would connect Mira Road with Line 4.
Kashigaon
Current terminus, serving Kashimira and Mira Road. Phase 2 continues from here to Bhayandar.
Subhash Chandra Bose Stadium
Future terminus in Bhayandar, where the proposed Line 13 would continue north to Virar.
Plan your trip
Mira Road to Andheri (E)
Mira Road to Borivali (W) / Andheri (W)
- Take Line 9 to Dahisar (East)
- Change to Line 2A
- Ride towards Borivali (W), Malad (W) or Andheri (W)
Phase 2: Kashigaon to Bhayandar
The second phase extends Line 9 from Kashigaon to Subhash Chandra Bose Stadium in Bhayandar, adding four stations: Sai Baba Nagar, Deepak Hospital (Medtiya Nagar), Shaheed Bhagat Singh Garden and Subhash Chandra Bose Stadium. MMRDA says civil work is about 96% complete. The section still needs safety inspection and certification by the Commissioner of Metro Rail Safety (CMRS) before opening, which is expected around December 2026.
Once Phase 2 opens, Bhayandar residents will be able to ride directly to Andheri (East) on the Red Line, a trip that today depends on crowded Western line trains or congested roads.
Route map
See also: Mumbai Metro map โ all lines
Timeline
- 2019Construction begins on the Dahisar (East) โ Bhayandar extension of the Red Line.
- 7 April 2026Phase 1 (Dahisar East โ Kashigaon) inaugurated.
- 8 April 2026Phase 1 opens to passengers, with through trains from Gundavali via Line 7.
- October 2026Phase 2 civil work about 96% complete; CMRS inspection pending.
- NextPhase 2 to Subhash Chandra Bose Stadium (Bhayandar), expected around December 2026.
About Metro Line 9
Route explained
Line 9 starts at Dahisar (East), where it meets Line 2A and Line 7, and runs north along the Western Express Highway corridor into Mira Road through Pandurang Wadi, Miragaon and Kashigaon. Phase 2 turns west towards Bhayandar, ending near Subhash Chandra Bose Stadium.
It is the first metro line to serve the Mira-Bhayandar municipal area, one of the fastest-growing suburbs in the region.
Line 9 vs Line 7
| Line 9 | Line 7 | |
|---|---|---|
| Route | Dahisar (E) โ Bhayandar | Gundavali โ Dahisar (E) |
| Length | About 11.4 km | 16.5 km |
| Stations | 8 (4 open) | 14 |
| Status | Partly open | Fully open |
| Through trains | Yes, Gundavali โ Kashigaon | Yes, Gundavali โ Kashigaon |
Both lines form the Red Line. See Line 7 for the stations south of Dahisar.
Project & technical details
| Item | Details |
|---|---|
| Length | About 11.4 km, fully elevated |
| Stations | 8 |
| Line colour | Red |
| Project authority | MMRDA |
| Operator | MMMOCL |
| Phase 1 | Dahisar (E) โ Kashigaon, about 5 km, opened April 2026 |
| Phase 2 | Kashigaon โ Subhash Chandra Bose Stadium, expected December 2026 |
Upcoming events in Mumbai
- 27NOVDiljit Dosanjh โ Aura India Tour, Mumbai
- 8โ9DECFred again.. โ Mumbai
- 12โ13DECRolling Loud India 2026
- 18โ19DECSunburn Festival Mumbai 2026
Frequently asked questions
Is Mumbai Metro Line 9 open?
Partly. The first four stations, from Dahisar (East) to Kashigaon, have been open since 8 April 2026. The remaining four stations to Subhash Chandra Bose Stadium in Bhayandar are expected around December 2026, after safety inspection.
What are the Line 9 timings?
Trains run from about 5:50 AM to 11:00 PM, every six minutes or less at peak times. Timings can change, so check the MMMOCL app before travelling.
What is the fare on Metro Line 9?
Dahisar (East) to Kashigaon costs โน20 and Pandurang Wadi to Kashigaon โน10. A direct trip from Gundavali (Andheri East) to Kashigaon costs โน50.
Can I travel directly from Andheri to Mira Road by metro?
Yes. Line 9 runs as a continuation of Line 7, so trains go directly from Gundavali in Andheri (East) to Kashigaon without changing at Dahisar (East).
How many stations does Line 9 have?
Eight elevated stations in total, of which four are open: Dahisar (East), Pandurang Wadi, Miragaon and Kashigaon.
When will Line 9 reach Bhayandar?
Phase 2 from Kashigaon to Subhash Chandra Bose Stadium is about 96% complete and is expected to open around December 2026, once the Commissioner of Metro Rail Safety approves it.
Where can I change from Line 9 to other lines?
At Dahisar (East) for Line 2A (towards Borivali, Malad and Andheri West). Line 7 trains continue through without a change.
Is Line 9 the same as Line 7?
Both are part of the Red Line. Line 7 runs from Gundavali to Dahisar (East), and Line 9 extends it north to Mira Road and Bhayandar, with through trains on both.
Who operates Line 9?
Maha Mumbai Metro Operation Corporation Ltd (MMMOCL). MMRDA is the project authority.